Baldwin Road – Phases 1 and 2
Project Name Baldwin Road – Phases 1 and 2
Location Baldwin Road from Morgan to Waldon, Orion Township
Owner Road Commission for Oakland County and Orion Township
Value $31,273,387.00
Project Photos












Project Scope
- Removal of 90,000 SYD of HMA pavement and construction of 83,000 SYD of Concrete Pavement
- 162,000 CYD of Earth Excavation and 120,000 CYD of embankment
- Placement of 70,000 Ton of aggregate base courses
- Installation of 54,000 FT of underdrain
- Installation of 24,800 FT of 12” – 84” storm sewer
- Installation of 10,700 FT of 8”-16” water main, including 1,000 FT of directional drill installation
- Construction of 5 HAWK Crosswalk Signalized intersections
- Removal and replacement of 128 FT of a 6’ x 4’ box culvert
Project Details
The Baldwin Road projects consists of the replacement of an existing two lane asphalt road with a 4 lane boulevard concrete roadway. Additionally, five round abouts are being constructed to improve traffic flow throughout this corridor. Phase 1 was started in late 2017 with Phase 2 completed in October 2020.