|

12955 23 Mile Road
Shelby Township Michigan 48315
586.254.2040














| |
South Access Road (SAR) Element #4
This
$20,000,000.00 plus, project was
awarded to Dan's Excavating, Inc. (DEI), in December
of 2000. The project was the final link in the new airport roadway system that
enables access to the existing terminals on the North side of the airport and
the new Midfield Terminal, from either the North or South end of
the airport.
The project was a challenge from the outset. While the contract
had a two year duration, the intermediate completion dates required that
approximately 95% of the project be built the first year. What this entailed
was constructing a complete traffic interchange inside one of the busiest
airports in the country without interrupting traffic flow or impacting aircraft
movement.
-
This required removing approximately 26 acres of concrete and bituminous
pavement ranging from 16" thick concrete apron pavement down to parking lot
paving of 4" thick asphalt.
-
This also meant that the majority of the 130,000 m3 plus of
excavation and embankment work took place inside the airport security area,
immediately adjacent to an active taxiway and operating aircraft ramp area.
-
In addition to the aircraft operation, the installation of just under three
miles of new storm drainage, water mains,
the construction of four bridges, and 80,540 square feet of retaining walls had to
be staged around the public traffic that flowed 24 hours a day, requiring a
substantial portion of the work to be constructed at night.

DEI was able to interface our work with all of the known and
unknown obstacles and schedule our sub-contractors to have the roadway ready for
public use in early December of 2001, three months prior to the opening of the
new Midfield Terminal.
Project Manager Rick
Kincaid
Project Superintendent Duane Holdwick |